Article
Publication date: 7 September 2012

Juha Haakana, Jukka Lassila, Tero Kaipia, Jarmo Partanen, Juha Lohjala and Hanna Niemelä

Underground cabling has become a true alternative in construction of electricity distribution networks, even in rural areas. The increasing amount of underground installations…

Abstract

Purpose

Underground cabling has become a true alternative in construction of electricity distribution networks, even in rural areas. The increasing amount of underground installations requires strategic work that helps to define the most profitable cabling targets. The purpose of this paper is to introduce a methodology to consider the underground cabling process.

Design/methodology/approach

The paper proposes a cabling concept that covers the issues on how cabling should be carried out. The analysis is based on techno‐economic and reliability analyses. The methodology consists of several steps that together constitute the concept.

Findings

The underground cabling concept comprises several steps that can be simplified into questions: where, what, when and how the network cabling process is carried out. The analysis of these questions and the related features of the network show that different approaches to the renovation can cause significant differences in profitability between the renovation strategies.

Research limitations/implications

The underground cabling concept provides a method to analyse the cabling process, and it contains several alternatives for applying the concept. Thus, the applicability of a certain method depends on the network and the objectives of the distribution system operator.

Practical implications

Renovation planning of the network has become common in distribution companies. Traditionally, ageing of the network has been the driver for the renovation. However, in the future, the scope of renovation planning should also include other renovation drivers, such as reliability.

Originality/value

The methodology proposed in the paper can be applied in the renovation and development process of distribution networks. The results are universal in the electricity distribution.

Details

International Journal of Energy Sector Management, vol. 6 no. 3
Type: Research Article
ISSN: 1750-6220

Keywords

Article
Publication date: 22 November 2011

Jukka Lassila, Tero Kaipia, Juha Haakana and Jarmo Partanen

The purpose of this paper is to establish a methodological framework to address key issues in electricity distribution network development. The paper defines subtasks in the…

1275

Abstract

Purpose

The purpose of this paper is to establish a methodological framework to address key issues in electricity distribution network development. The paper defines subtasks in the strategy process and presents key elements in the strategy work and long‐term network planning. The results are illustrated by a case network.

Design/methodology/approach

The paper describes the methodology for cost and reliability analyses in the strategy work. The focus is on techno‐economic feasibility of certain network development technologies in the network strategy and the surveys are linked to economic regulation, specifically to reliability of supply and allowed return. The study addresses the stages of strategic decision making and compilation of investment strategies.

Findings

The strategic planning concept and methods are applicable in practice; the results have proven valuable in the long‐term business development and in discussions with the company owners. Outage costs are an essential element in the economic regulation of the business, reliability being a key driver in network planning.

Research limitations/implications

There is no universal solution to strategic decision making, but each development task is highly case specific. This is due to diverging operating environments and targets set by the company owners; these issues strongly influence the strategy process.

Practical implications

The work illustrates strategic planning in an actual distribution company and shows how the methodology can be applied to the strategic network development. Nevertheless, the results cannot be generalised as such, but each network has to be considered individually.

Originality/value

The proposed concept can be applied to the long‐term development of distribution networks. The results are internationally applicable, yet diverging regulatory models call for specific methodology in each country.

Details

International Journal of Energy Sector Management, vol. 5 no. 4
Type: Research Article
ISSN: 1750-6220